Complete gas piping installation and pressure test.
Complete the Cedar City Gas Clearance Form before the inspection.
Schedule a gas clearance inspection online. This can be done in conjunction with 4 way/ rough inspection.
Please attach gas clearance form to online permit or have gas clearance form on the job site located by the gas meter main pipe at the time of inspection.
Contact Rocky Mountain Power at 888-221-7070 to obtain the necessary work order numbers. You will need a work order number for each meter base for temporary power. Then you will need another set of work order numbers for permanent power. **Temporary and Permanent power numbers will not interchange.
Complete electric meter service rough installation.
Schedule a temporary or permanent power inspection online. At the time of inspection, you will need to put the work order number in the inspection notes. **Inspection and re-inspections will not be scheduled without the work order number.