Construction will continue through October. This project will reconstruct Cross Hollow Road and reconfigure the I-15 interchange to a diverging diamond interchange (DDI). These improvements will accommodate future travel demand and improve safety.
Restrictions for This Week
Northbound and Southbound I-15
• NEW - Traffic will be restricted to one lane in each direction at all times from Monday, May 12 through Thursday May 22. Please note that this includes the weekend of May 17 and 18, as well as nights. The additional lane restriction times will allow crews to complete work in advance of the Memorial Day holiday. All I-15 lanes will be open from Friday, May 23 through Monday, May 26.
NEW On Wednesday, May 14, crews will restripe and shift traffic toward the median to accommodate work on the right shoulders. This work will not have any additional lane impacts.
Cross Hollow Road
• Eastbound traffic will continue to be reduced to one lane. Consider using an alternate route to avoid delays.
• Intermittent flagging operations will be used to accommodate trucks entering and exiting the work zone.
Diverging Diamond Interchange (DDI)
Want to know more about how the final interchange will function? Visit the project website, www.udot.utah.gov/go/southcedar, to view videos of DDI’s around the state.
Construction Zone Safety
Beginning April 1, the speed limit on I-15 will be reduced within the project limits. Please observe the lowered speed limit for your safety and that of the construction crews.
Questions or Concerns
If you have a question or concern regarding the project, please contact me and I’ll be happy to assist you.
Carlye Sommers
Public Involvement Manager
855-415-3923
southcedar@utah.gov