Ongoing Restrictions
Crews will shut down operations at noon on Thursday, July 3rd and resume work on Monday, July 7th in observation of the 4th of July holiday.
Northbound and Southbound I-15
I-15 will have intermittent one lane closures as needed, Monday through Friday, throughout the summer.
Cross Hollow Road
On Monday, July 7th, crews will shift traffic to the south side of Cross Hollow Road. Motorists can expect the usual lane restrictions but should pay close attention to construction signage as the work to shift traffic takes place. This shift will place traffic on new pavement and allow for the reconstruction of the north side of Cross Hollow.
Traffic will continue to be reduced to one lane in each direction. Consider using an alternate route when possible.
Pedestrians should use the designated sidewalk and should not enter Cross Hollow traffic lanes at any time.
Main Street
Traffic will be shifted to the west side of Main Street on Monday, July 7th, in conjunction with the Cross Hollow Road traffic switch.
DDI Visualizations
Take a few moments to visit the project website and view the DDI visualizations. These videos are a great way to learn how the DDI functions and prepares drivers for the new configuration that will be opening in late August.
4th of July
Work will not take place between noon on July 3rd and the morning of July 7th. We hope everyone has a safe and happy holiday.
Please let me know if you have any questions or concerns.
Carlye Sommers
Public Involvement Manager
855-415-3923
southcedar@utah.gov