[ARCHIVED] Construction on South Cedar Interchange, Sept. 12 Update

Ongoing Restrictions

The project is currently on schedule to be complete in early October. The following restrictions will be in place until that time.

Northbound and Southbound I-15
I-15 will have intermittent one-lane closures, as needed, Monday through Friday.

Cross Hollow Road
Traffic will be restricted to one lane in each direction to provide space for crews to construct islands, barrier, and walls. Pedestrians should use the designated route and should not enter Cross Hollow traffic lanes at any time.

Intersection of Cross Hollow Road/Highway 91 and Main Street
Drivers should pay close attention to lane configurations, locations of stop bars, pavement markings, signs and traffic signals. Use caution and be patient when navigating the intersection.
DDI and GPS

We have received reports that GPS providers have not updated their maps to the new DDI configuration. Please do not follow the GPS directions when traveling through the work zone, instead follow the signage and striping. In time, GPS providers will update the route.

Please let me know if you have any questions or concerns.

Carlye Sommers
Public Involvement Manager
855-415-3923
southcedar@utah.gov

Video of current construction
Facebook Twitter Email

Other News in Cedar City Updates

Website thumbnails (10)

WATCH CITY COUNCIL ON YOUTUBE

Posted on: March 24, 2020
Public Hearing Notice (1)

PUBLIC HEARINGS & NOTICES

Posted on: May 12, 2020
Notice of Election 2023

NOTICE OF ELECTION

Posted on: March 29, 2023
Water Restrictions Rate Increase

WATER RESTRICTIONS & RATE INCREASE

Posted on: March 24, 2023
Upcoming Events

UPCOMING EVENTS

Posted on: January 19, 2023
Connect with Us (1)

CONNECT WITH US!

Posted on: June 27, 2022